Design from the product outwards
An efficient conveyor system is not chosen from a catalogue and then fitted into a building. It is designed from the product and the process outwards: what has to move, how many, how fast, between which points, and what happens around it. The equipment comes last. This guide sets out the design sequence ENTRA’s engineers follow on factory projects, with the questions to answer at each step and the deliverables that should come out of it.
Step 1: collect the data
Most design errors trace back to missing or optimistic data. Before any layout is drawn, collect:
- Products: every product and pack format, with dimensions, mass, base, stability and fragility; the smallest, largest, lightest and heaviest cases; future formats already planned.
- Rates: normal, peak and target rates for each product, in products per minute or tonnes per hour, and the shift pattern.
- Process: the sequence of operations, the machines involved with their rated speeds and infeed and outfeed heights, and where people work.
- Building: layout drawings, columns, doors, floor levels and load capacity, ceiling height, existing services, routes for forklifts and pedestrians.
- Environment: temperature, humidity, dust, washdown, food contact, hazardous areas.
- Utilities and standards: power supply, compressed air, the client’s preferred component brands, safety and documentation requirements.
A site visit to see the current line and talk to operators and maintenance staff is part of this step; it usually reveals constraints that are not on any drawing.
Step 2: calculate rates, speeds and buffers
Turn the rates into conveyor speeds using the product pitch, and check that every conveyor, transfer and machine can sustain the peak rate. Identify the critical machine and decide where buffers are needed and how large; see accumulation conveyor systems. For the formulas, use our speed, capacity and throughput guide.
Illustrative example, not an ENTRA project
A line must produce 24 cases per minute at peak. Cases are 300 mm long and the case packer needs a 100 mm gap: pitch 0.4 m, minimum speed 24 × 0.4 = 9.6 m/min. The conveyors after the case packer are designed for about 11–12 m/min so that they can clear a backlog after short stops, and an accumulation conveyor before the palletiser holds the cases produced during a typical pallet change.
Step 3: develop the layout concept
- Arrange the route in process order, as straight and short as the building allows, without crossing forklift routes where possible.
- Use height where it helps: overhead conveyors, mezzanines or vertical conveyors can free floor space and separate people from material flow.
- Keep transfers to a minimum; every transfer is a potential jam point.
- Leave access for operators, maintenance and cleaning, and space for future extension.
- Prepare two or three alternatives and compare them on cost, space, flexibility, risk and ease of installation.
3D models help everyone understand the concept, check clearances and spot clashes with services early.

Step 4: select conveyor types and components
For each section of the route, select the conveyor type that suits the product and duty (belt, roller, chain, modular, vertical, spiral, screw), then the key components: belt or chain, rollers, drives, frame material and finish. Our guide to industrial conveyor systems compares the types. Standardise components across the system where possible to simplify spare parts and maintenance.
Step 5: design the controls
Define the control architecture, the start and stop sequences, how the conveyors respond to each machine’s state, the buffer logic, the operator interface and any data connections to plant systems. Write the interface specification with each machine supplier at this stage, not during commissioning. See industrial automation and conveyor integration.
Step 6: risk assessment and ergonomics
Carry out the risk assessment on the concept, not after installation. The process of ISO 12100 identifies hazards (nip and shear points, falling loads, crossing traffic, access for cleaning) and reduces them by design first, then by guards and protective devices, then by information [1]. Guard openings and distances follow ISO 13857 [2], and the electrical equipment follows IEC 60204-1 [3]. Where conveyors replace manual lifting, use the limits for manual lifting, lowering and carrying in ISO 11228-1 to set working heights and loads for the tasks that remain [4].
Step 7: detailed design and documentation
- General arrangement and detail drawings, bill of materials.
- Structural checks for frames, supports, platforms and floor loads.
- Electrical schematics, panel layouts, cable lists, PLC and HMI software.
- Risk assessment record, safety function list and validation plan.
- Test plans for factory and site acceptance.
- Operation and maintenance manuals, spare parts list.
Step 8: manufacture, test, install and commission
- Manufacture with quality checks on materials, welding, finishing and assembly.
- Factory acceptance test (FAT): run conveyor sections and control panels before shipment where possible, against the agreed test plan.
- Installation: planned around the client’s production, often in shutdown windows; levelling, alignment and anchoring.
- Commissioning: I/O checks, direction and speed checks, interface tests with each machine, safety function validation.
- Site acceptance test (SAT) and performance run: rates and functions demonstrated with real products.
- Handover: documentation, training for operators and maintenance staff, spare parts.
Design principles that save money later
- Design for the worst product, not the average one.
- Fewer transfers, better transfers.
- Buffers where stops happen.
- Maintenance access is part of the design.
- Standard parts where possible, special parts only where needed.
- Room to grow: spare capacity in drives, panels, software and floor space for the next step.
Design review checklist
Before the design is frozen, review it with production, maintenance, quality and safety staff. Typical questions:
- Does every product and format run through every transfer without tipping or jamming?
- Are rates checked at peak, including recovery after stops?
- Where will operators stand, walk, load and unload, and are heights and reaches comfortable?
- How is each conveyor cleaned, and how long will cleaning take?
- Can belts, chains, drives and rollers be changed without dismantling the line?
- Are emergency stops within reach everywhere, and is it clear what each one stops?
- How will forklifts and pedestrians cross the conveyor route?
- What happens during a power failure and on restart?
- Where will the next machine or the next line go?
Common design mistakes
- Optimistic data: designing for the product samples provided, not for the full range that production will use.
- Too many transfers: each one adds risk of stoppage and damage.
- No buffer before slow or unreliable machines.
- Controls designed late: machine interfaces discovered during commissioning.
- Forgotten access: drives, take-ups and sensors that cannot be reached safely.
- No allowance for installation: sections too large to bring into the building, or installation planned without the production shutdown it needs.
How ENTRA works
ENTRA works as a turnkey provider: mechanical, electrical and controls engineers, project managers and account managers work with the client on the specific problem. We study the current line, propose a solution that shortens the material path, cuts losses and raises output, and then supply, install and support it [5]. Our case studies show examples from real plants, and the 3D equipment gallery lets you explore equipment before the design starts.
Frequently asked questions
What is the first step in designing a conveyor system?
Collecting data: the products and their variations, required rates and peaks, the process steps, the building layout and constraints, and the interfaces with machines and people.
How long does it take to design and install a conveyor system?
It depends on size and complexity. A single conveyor may take weeks; a full line with controls, transfers and machine integration takes longer. A realistic schedule is agreed after the data collection and concept stage.
Should the conveyor be designed for the current or future rate?
Design for the current rate with a clear margin, and plan the layout, drives, controls and floor space so that a known future rate can be reached by upgrading rather than replacing.
What is a factory acceptance test for a conveyor?
A test, agreed in advance, that checks the conveyor or line against the specification (rates, functions, safety, documentation) before it is accepted. A site acceptance test repeats the key checks after installation.
Sources and references
- Pilz, Overview of generic machine-safety standards (EN ISO 12100, ISO 13849, ISO 14120, ISO 14119, IEC 60204). Checked 28 Nov 2026.
- ISO, ISO 13857:2019 Safety of machinery — Safety distances to prevent hazard zones being reached by upper and lower limbs. Checked 28 Nov 2026.
- IEC / AFNOR, IEC 60204-1:2016 Safety of machinery — Electrical equipment of machines — Part 1: General requirements. Checked 28 Nov 2026.
- ISO, ISO 11228-1:2021 Ergonomics — Manual handling — Part 1: Lifting, lowering and carrying. Checked 28 Nov 2026.
- ENTRA Electromechanical, About ENTRA (company history, scope and certifications as published by ENTRA). Checked 28 Nov 2026.
Sources are listed for technical accuracy. Names of standards bodies, regulators and manufacturers appear only to credit the source; ENTRA does not claim their products or specifications as its own.
Copyright © 2026 ENTRA. All Rights Reserved. Text, calculations and original graphics on this page may not be reproduced without permission.